|
NATIONAL INTEGRATED DEVELOPMENT STRATEGY PROCESS
PROGRAMME OF ACTIVITIES
1. INTRODUCTION
The main objective of the National Integrated Development Strategy (NIDS)
is to improve the longevity, quality of life and income of the people of
the British Virgin Islands (BVI). This planning strategy will integrate
economic, social, physical and environmental objectives in a simultaneous
fashion to obtain a more sectorally balanced and sustainable development
pattern. To achieve this objective, an integrated planning framework built
upon the concept of strategic visioning from the political leadership and
impacts of public and private sector to fashion policies, strategies,
programmes / projects in a participative manner will play a central role.
The integrated framework requires the interaction of a number of
stakeholders in different activities at different stages. This interaction
and these activities comprise the process of the project. This paper is a
documentation of the all process involved. The documentation will help to
evaluate the project and development methodology guide for future
development. The documentation of process includes all activities involved
in all phases of the project.
2.0 OPERATING MECHANISM:
The operating mechanism for the preparation of the NIDS, consists of two
interrelated components which are the methodological framework, which
outlines the approach and the process or set of activities leading to the
development of strategy and the second component is the institutional
framework which outlines the network of human resources necessary for the
elaboration of an integrated strategy and resulting plan i.e. management
process.
These two components interact to form the process for the development of
the NIDS. Six major phases are identified and are represented in a
grouping of the major activities and tasks as follows:
-
Conceptualization
-
Analysis
-
Strategy Formulation
-
Approval
-
Implementation
-
Monitoring and Evaluation
The major activities of each phase are presented below.
These activities represent those that have been undertaken to date as well
as those to be undertaken in subsequent phases.
2.1 PHASE I: CONCEPTUALIZATION OF THE PROJECT
During this phase a vision and broad national goals were identified. The
project scope is clarified, a draft conceptual framework and methodology
were developed and outline work plan is prepared.
Phase one has been completed.
The following activities took place:
Activity 1: Political Support of NIDS (April 1992)
The political directorate through the Chief Minister in the April 1992
budget address initiated the process of development of the NIDS. This was
manifest by the concern expressed for the absence of a national plan in
the territory.
Activity 2: Symposium on Planning Priorities (November 1992)
To advance the conceptualization of the project a symposium was organized
by the Chief Minister's Office in collaboration with the Development
Planning Unit (DPU) in November 1992. The aim of the symposium was to
chart the national planning priorities. A concept paper entitled National
Integrated Development Plan 1994-1998 was presented. This paper set out
preliminary objectives and scope of the proposed plan and the intended
approach for its elaboration. It also defined the major elements, the
vision and set out a schedule of activities leading to the finalization of
a NIDP by December 1993. The Ministers, Permanent Secretaries, Members of
the Planning and Projects Review Advisory Committee (PPRAC) attended this
symposium.
Activity 3: Development of the Project “NIDS” (May 1995)
The development of the project was pursued through the technical
assistance from International agencies. Assistance was sought from United
Nations Development Programme (UNDP)/United Nations Centre for Human
Settlement (UNCHS) in the elaboration of the process and development of
the strategy project document was signed by Government BVI and UNDP/UNCHS
on May 1995.
Activity 4: Mobilization of Resources for the Project (June 1995 –
February 1996)
The Government of the British Virgin Islands and UNDP/UNCHS collaborated
in the mobilization of financial and human resources for the project. UNDP/UNCHS
provided the Project Manager, Consultants and four United Nations
Volunteers to work in the Town and Country Planning Department,
Development Planning Unit and Conservation and Fisheries Department. The
BVI Government provided over 80% of the financial resources as well as
counterpart professional staff.
Activity 5: Development of Preliminary Work Programme (March 1996)
The Project Coordinator and Project Manager jointly developed a
preliminary work programme. The work plans were based on activities
indicated in the project document. The initial work programme should have
started in March 1996 and ended up in April 1997.
Activity 6: Formation of Project Management Team: March, 1996)
The Chief Minister’s Officer appointed the Project Management Team. This
group is a pillar of the project. It is responsible for day-to-day
coordination of the project. Because of the inter-sectoral nature of the
project, the chairman of the group is the Head of the Development Planning
Unit. Other members are Chief Physical Planning Officer, Head,
Conservation and Fisheries, Head, Social Development. Initially these were
the members, later it was decided to include more members in the group.
The additional members are the Permanent Secretary/Chief Minister's
Office, Assistant Secretary, Ministry of Health and Welfare and Financial
Secretary. The original secretary of this group was UNCHS Project Manager.
Up on the expiration of her contract the Project Administrator contracted
by the Government of the British Virgin Islands filled this position. This
group meets every Wednesday to review the progress of the project. In
general the group is responsible for provision of administrative and
technical services and coordination of all sub-committees.
Activity 7: Public Workshop on NIDS (November 1996)
The workshop was organized by UNDP in collaboration with the BVI
Government to sensitize heads of public and private sector and
Non-Governmental Organizations by briefing them of their role and the
objectives of the project, project justification, implementation
strategies and the expected results of the project. Two facilitators made
presentations at this workshop. Dr. James Armstrong, the Project
Coordinator UNCHS-Barbados and Mr. Winston Dookeran from UN ECLAC-Trinidad.
These facilitators were supported by members of the Project Management
Team. Suggestions from the participants were taken and included in the
project process.
Activity 8: Formation of Sub-Committees and Secretariats (March,
-1997)
The Project Management Team in collaboration with the office of the Chief
Minister set up a number of sub-committees to examine different
sectors/areas of study of the economy with a view to assist in the
formulation of policies and strategies. Members of these committees are
from public and private sectors. The letters of appointment were signed by
the Chief Minister.
The functions of the subcommittees are:
-
Evaluation of all information in the relevant
sector/area.
-
Identification of any further data that is required.
-
Examination of the existing data with a view to the
identification of needs in the sector / area which foster sustainable
development of the territory.
-
Development of goals and objectives for the particular
sector/area, which can foster sustainable development of the
territory.
-
Development of policies and strategies for the
particular sector/area.
-
Assisting the public consultations with respect to the
area/sector.
-
Identification of programmes / projects for the
particular area.
The following sub-committees were formed:
-
Global External Sub-Committee:
Responsible for Information, Political Relationship, Science and
Technology.
-
Global Domestic Sub-Committee:
Responsible for Population, Habitat, Government, macroeconomics and
Environment.
-
Productive or Economic Sector Sub-Committee (I):
Responsible for Agriculture, Fisheries, Mining and Quarrying and
Construction.
-
Productive or Economic Sector Sub-Committee (II):
Responsible for Tourism
-
Productive or Economic Sector Sub-Committee (III):
Responsible for Financial Services
-
Social Service Sub-Committee:
Responsible for Education, Culture, Health, Social Development and
Sports.
-
The Physical Infrastructure Sub-Committee:
Responsible for Communications, Transport, Energy, Water and Sewerage.
The Project Management Team did the appointments of
secretariats of the above committees. The secretariats provide technical
and secretarial services for the sub-committees, which includes the
following.
-
Researching on the sector / area.
-
Technical input and interpretation as required.
- Provision of all relevant documents and papers.
- Organization of the meetings in conjunction with the chairperson.
- Arrangement for all meetings, which includes the preparation of
agendas, and circulation of minutes, notes and reports.
- Preparation of final reports in conjunction with the chairperson.
Activity 9: Training Workshop on Strategic Planning for
Integrated Development Planning - January 1997.
The Government of the BVI/ UNDP/ UNCHS in collaboration with the
University of the West Indies organized a training workshop for one week
on “STRATEGIC PLANNING FOR THE INTEGRATED DEVELOPMENT PLANNING”. The
aim of the workshop was to expose the Project Management Team and Officers
dealing with the project to specific project management skills. Among the
topics they learned includes the following:
- Strategic Planning as a tool in the integrated planning process.
- Integrated Planning System.
- Strategy Implementation.
- Tools for Situation Analysis.
- Development and Using Integrated Planning Framework.
- Project Planning and Development.
Activity 10: Formation of Strategic Change Team
This team is supposed to be appointed by the Chief Minister. The Project
Management Team has proposed names of the members of this team, but their
letters of appointment have not yet been issued.
2.2 PHASE II: ANALYSIS
This phase provides the research base for the design and implementation of
the national development strategy. Basically this phase focused on
preparing the base of the study, including the identification of the
critical dynamics of society, key variables and factors, analysis of the
actors and their roles, and the identification of strengths, weakness,
roles and threats facing the country. The studies cover the economic,
social, physical and environmental components.
Activity 1: Data Collection
This exercise involved primary and secondary data collection, which
includes gathering of data, facts and information. Apart from collecting
information officers were also involved in interviewing relevant officials
in the line ministries, departments and public organizations to obtain
views and their inputs in this project. Among the data collected are
sectoral policies, strategies, programmes and projects being implemented.
The agencies involved in this exercise were key departments, members of
subcommittees and secretariats. These series of data were collected from
the following areas/sectors: Communication and Transport, Energy, Water
and Sewerage, Drainage, Construction, Agriculture, Fisheries, Mining and
Quarrying, Distributive Trade, Tourism, Social Development and Sports,
Population, Environment, Habitat, Government, Money and Banking,
Government Finance, Balance of Payments and Science and Technology.
Activity 2: Data Analysis
Departments/Sub-committees played a major role in compiling and analyzing
the data gathered in Activity 1. The analyses were in a form of
development trends of each study area/sector, analyses of polices and
strategies linkage among the sectors. Interactions between factors were
carefully analyzed, trends identified and examined. At the end of this
activity an overview emerged as to how things had evolved, what the
present situation is like and how they are most likely to develop in the
future. From the analysis a draft of proposals were made to be included in
the background papers.
Activity 3:Writing of Background Papers:
Departments / Sub-Committees / Secretariats was involved in this exercise.
The analysis made in Activity 2 was used to formulate the background
papers. The Project Management Team recommended the following format for
all background papers.
- Introduction: Definition and brief description of the sector
or study area.
- Background: Covered historical background of the study
related to present situation and future development.
- Situation Analysis: Recent development of the sector / study
area. The focus was mainly on economic, social, physical and
environmental analysis.
- Problems / Constraints / Issues: This area covered problems
and constraints of each sector / study area e.g. resources allocation,
management / administration, assessment of resources and other
elements were addressed in this part.
- Sectoral Goals and Objectives: On this section goals and
objectives of the sector / study area were identified. Priorities of
needs were identified and the integration processes with other sectors
of the economy were also identified.
- Polices and Strategies: Policies of each sector / study area
were identified in order to promote the performance of the sector /
study area. After policies were formulated, strategies were identified
on how to implement the policies identified.
- Programme and Projects: Programme and Projects, which will
try to solve/address problems, were identified. Writing of projects
and programmes followed the World Bank format.
Activity 4: Project Data Bank Process:
This activity was carried out through a consultant sponsored by CFTC in
collaboration with Development Planning Unit. Already the National Project
Data Bank logical design system guide document has been produced.
Activity 5: Review of Background Papers by Sub-Committees
In some cases where the subcommittees were not directly involved in
writing the background papers. They were required to review these papers
by making changes as deemed necessary. This exercise was complete in
March, 1998.At the end of the exercise, revised background papers were
produced.
Activity 6: A Visit by Development Economist to assist with the
Preparation of NIDS
- During the first visit the Development Economist advised the Project
Management Team on sector/study area paper outline, the documentation
of the process of NIDS and work plan for the project.
- The second visit of the Development Economist was devoted to the
following:
-Revision of Conceptual Framework of the project. A revised document
has been produced.
-Revision of some of the background papers and the project data.
- The third and fourth visits were devoted on assisting the PMT in
preparation for the Retreat to discuss main Issues and Strategies
emanating from research and analysis conducted by Sub committees /
Secretariats. The Development Economist was the main facilitator of
the Retreat.
- The fifth visit the Development Economist presented to the PMT a
draft structure document to be used for Public Consultation.
- The sixth visit the Development Economist was involved in public
consultation exercise for two weeks (from 2nd June, to 12th June,
1998).
- August to September, 1998- Preparation of the first draft of the
document.
- October 1998: Submission of the first draft to the Project
Management Team.
Activity 7: Documentation of the NIDS Process
The UNV Development Planner undertook the continuous documentation of the
NIDS process. The documentation started from the time when the project was
conceptualized up to date. The document shows all the phases and all
activities undertaken.
Activity 8: Review of all Sectoral / Area Papers
The Project Management Team was supposed to review all sectoral / area
papers submitted by the subcommittees.
Activity 9: Synopsis and Identification of Major Issues
The retreat was organised by the Project Management Team with the guidance
provided by the Development Economist (Consultant) .The retreat was held
at Long Bay Beach Resort .The main objective of the retreat was to develop
consensus on the main issues and strategies emanating from the research
and analysis conducted by the sub committees / secretariats. The research
analysis incorporated twenty-eight areas of study, divided into four broad
divisions i.e. Economic, Social, Spatial and Environment. Over forty
participants from Government Departments, Public and Private Institutions,
Non Governmental Organizations and representatives from UNDP, UNCHS and
CARICAD participated in the retreat. The following are the outcome of the
retreat;
- The main Issues and Strategies were identified.
- The Mission Statement of the Government of BVI were defined i.e. To
facilitate and improve quality of life for all the people in the
territory by ensuring their health, education, productivity,
cohesiveness, resilience and global competitiveness in a responsible,
integrated and sustainable manner.
- The Vision Statement were defined i.e. To create a society that is
globally competitive and socially cohesive with ability to satisfy the
basic needs of all the people by upholding the principles of human
rights and good governance by managing a sustainable and integrated
way the development of natural and human resources of the Territory,
by generating self confidence among the people and maintaining the
unique cultural identity of the BVI.
- The main objectives of NIDS were identified i.e. to improve the
quality of life of the people of the BVI.
- The key Strategies for Integrated Development of the BVI was
identified.
Activity 10: NIDS Publicity Campaign: January to April, 1998:
This exercise was aimed at educating the public about NIDS before the PMT
went for Public Consultation in May 1998. The PMT in collaboration with
the Chief Information Officer organised the media campaign. Before that
the Project Coordinator briefed the media about NIDS, the purpose was to
educate and familiarise the media about NIDS so that they can report
effectively to the public. Also weekly newspapers produced supplements
information about NIDS. The media campaign continued up to May and
included the following;
- Two appearances by two key persons from the PMT on Public Eye,
government’s weekly call in programme, both of which were re-aired.
- Radio spots on three local radio stations.
- Monthly features on the almanac on ZBVI (radio) highlighted various
aspects and issues on NIDS.
- G.I.S. Radio report-Weekly radio interviews with key persons on
various issues of NIDS. Copies of which were provided to local media
for inclusion in their newscasts.
- Facts sheets that focused on various sectoral issues and were
distributed to several areas.
Activity 11: Public Consultation (From 2nd June to 17th July, 1998)
After the publicity campaign and education about NIDS, the Project
Management Team organised several meetings in different areas of the
communities so as to get public opinions / ideas / issues to be considered
in the plan in order to achieve the objectives of NIDS by year 2003.
WHAT HAS BEEN DONE?
From June 2nd, Public Consultation meetings were held in main centers of
the community i.e. Road Town, East End, West End, Virgin Gorda, Anegada
and Jost Van Dyke. Before the meetings were held a Public Consultative
Document (which was prepared by the consultant / Development Economist)
and key sectors brochures were distributed to the public to enhance their
knowledge about NIDS. The first meeting which was held in Road Town was
televised, the idea was once again to explain to the public the objectives
of NIDS, the benefits of NIDS and the role of the public as beneficiaries
of the of the programme. In general the meetings were intense and highly
participatory, and the public showed interest and commitment in the
programme. The issues / ideas / opinions gathered from these meetings will
be incorporated in the plan (NIDP).
Activity 12: Review of the first draft of the document (September/
October, 1998)
The Project Management Team spent this time reviewing the first draft of
the document submitted by the development economist. On 16th October 1998,
the PMT presented their comments to the Development Economist to be
included in the final document.
2.3 PHASE III: STRATEGY FORMULATION
This phase deals with development of broad strategies; goals and policies
based on the analyses of phase II. It will emphasize the need to design
and implement effective strategies to realize shared visions.
WHAT HAS BEEN DONE:
Draft Strategies are included in some of the background and sector papers.
During the Retreat these strategies formulated by the Sub Committees /
Secretariats were discussed fully and were endorsed by the participants.
More strategies were gathered from the public consultation exercise.
2.4 PHASE IV: APPROVAL
This phase will result in approval of the NIDS by Executive Council before
implementation.
WHAT HAS BEEN DONE:
The NIDS has been approved by Executive Council in October 2001.
2.5 PHASE V: IMPLEMENTATION OF THE PLAN
This phase deals with implementation of plans and programmes. The success
of this stage depends on the effective institutionalization of the process
and adequate capacity in terms of organization and human resources.
WHAT HAS BEEN DONE:
This will be dealt with after completing Phase IV.
2.6 PHASE VI: MONITORING AND EVALUATION
This phase constitute a strategic management process, which is monitoring
and evaluation of plans/project/programmes.
WHAT HAS BEEN DONE:
The final phase will be done after completing Phase V.
SUMMARY OF NATIONAL INTEGRATED DEVELOPMENT STRATEGY
(NIDS)
PROCESS
| PHASE |
ACTIVITIES |
AGENCIES/ INDIVIDUALS INVOLVED |
TOOLS/ MECHANISM |
PHASE No. I
Conceptualization of the Project |
(1) Political Support |
Political Directorate |
Budget Speech Statement |
| |
2) Symposium on Planning the BVI
Development with a Strategic Vision Approach (NIDP 1994-1998) |
( Ministers, Permanent Secretaries,
Members of Planning and Projects Review Advisory Committee (PPRAC). |
Workshop, Discussion and Brainstorming. |
| |
(3) Development of NIDS as a project. |
Government of BVI, United Nations
Development Programme (UNDP)/ United Nations Center for Human
Settlements (UNCHS). |
Consultation and Discussion. |
| |
(4) Mobilization of Resources for the
Project. |
Government of BVI, UNDP / UNCHS |
Budget, Project Document. |
| |
(5) Development of Preliminary Work
Programme. |
Project Coordinator and Project
Manager. |
Consultation and Discussion. |
| |
(6) Formation of Project Management
Team. |
The Chief Minister appointed Head
DPU, Head, TCPD; Head, C&FD; Head, SD; Later list included, PS/CMO;
AS, Min of HE&W; F.S Min of F; PS /Min. NL; Chairman of SDC and
AS/CMO. |
Consultation, Discussion and
Brainstorming. |
| |
(7) Public Workshop on NIDS. |
Heads of Public and Private Sectors,
and Non Governmental Organisations. |
Workshop, Brainstorming and Discussion. |
| |
(8) (I) Formation of Sub Committees.
(II) Formation of the Secretariats to the Sub- Committees |
Chief Minister with the advise of the
PMT appointed members from the Public and Private Sectors and
NGO’s.
The PMT Appointed members of the Secretariats for different
Committees. |
Consultation between the Political
Directorate and the PMT. |
| |
(9) Training Workshop on Strategic
Planning for Integrated Development Planning. |
The GBVI, UNDP/ UNCHS. organised the
Workshop for members of PMT and the Secretariats. |
Workshop, Brainstorming and
Discussion. |
| |
(10) Formation of Strategic Change
Team. |
To be appointed by Chief Minister |
Consultation between the Political
Directorate and PMT. |
| PHASE II ANALYSIS PROCESS |
(1) Data Collection |
Departments, Members of the
Secretariats. |
Interview, gathering of data/
facts/information. |
| |
(2) Data Analysis. |
Departments, Members of the
Secretariats. |
Researching, Reviewing the past and the
past trends. |
| |
(3) Writing Background/ Sector Papers. |
Departments, Members of the
Secretariats. |
Review and Discussion. |
| |
(4) Project Data Bank Formulation. |
Consultant Sponsored by CFTC and
Development Planning Unit (DPU). |
Research and adapt new process. |
| |
(5) Review of Background / Sector
Papers. |
Sub Committee Members. |
Discuss and Review the document. |
| |
(6) Review of the project
- Conceptual Framework
- Workplan
- Review Background Sector Papers.
|
Consultant / Development Economist. |
Consultation, Discussion,
Documents Review |
| |
(7) Documentation of the Process of
NIDS. |
UNV Development Planner in
collaboration with the Project Administrator. |
Review files / Documents, Discussion. |
| |
(8) Review of all / Background Sector
Papers. |
Project Management Team. |
Discuss, Review documents |
| |
(9) Synopsis and Identification of
Major issues and Strategies. |
PMT , Governments Heads, Key
Departments, Public and private Institutions, NGO’s,
Representatives from UNDP, UNCHS and CARICAD |
Retreat, Consultation,
Brainstorming, Discussing. |
| |
(10) NIDS Publicity Campaign |
Project Management Team, Chief
Information Officer, Media Institutions. |
News Papers, Radio broadcasts |
| |
(11) Public Consultation Meetings. |
Project Management Team, Members of the
public, Community groups, Institutions, and NGO’s. |
Discussion, Consultation and review the
document. |
| |
(12) Review the first draft of the
document. |
Project Management Team |
Discussion, consultation and review the
draft. |
| |
NIDS approval |
Executive Council |
Discussion / Debate. |
|