[text only]
Site Map
Forms & Payments
Questions & Answers

Home

Home













 

The
Development Planning Unit
Government of the British Virgin Islands


Public Investment>   Issues in Public Sector Investment> Report by Janelle Cox


Report by Janelle Cox


SUMMARY OF WEAKNESSES

Indications are that there is at the concept level, a process for managing and implementing the public sector investment programme. However, the system has weaknesses resulting from a lack of adherence to procedures and committees not functioning as originally envisaged. These weaknesses have contributed to poor project planning, design, management and implementation. The authorities at all levels breaching the regulations have further exacerbated this, which governs the system. The lack of sanctions- to apply at the various phases, especially implementation, has only contributed to a breakdown in the process.

In conducting some analysis, it was discovered that revoting of funds amounting to approximately $4.25 million took place on 51 projects for 1996. For financial year 1997, indications are that revoting of funds amounting to approximately $7.57 million took place on 126 projects. This represents a 78% increase, in monetary terms, over 1996 figures. This is an indication of either poor project design and planning, inflating of project costs, improper scheduling on projects or the lack of institutional capacity to implement and manage projects.

Analysis of the budget and the PSIP (1995-1998) reveals that approximately 67% of the budget is locally funded. It is also these projects which do not undergo any testing or go through the route of development and appraisal to determine if they are consistent with the priorities of the government as well as the medium and long-term national and sectoral plans. In so doing, the government is not in a position to determine if "it is getting value for money", or to conduct any concrete evaluation to assess if envisaged benefits are being derived and if the target group has accepted the development.

The institutional capacity to effectively and efficiently manage the process is insufficient and this is having a detrimental effect on the entire process. Changes may be recommended to the system in an effort to improve it, however these changes will have no impact if the issue of placing adequate and appropriate staff is not also addressed.

 

General

  • There appears to be a lack of knowledge of the procedures and policy guidelines for the effective operation of the project cycle management system. It is therefore necessary for these to be re-established and disseminated by DPU to the relevant officials at all levels. All ministries should be notified from the highest authority that DPU has responsibility for coordinating and seeing to the proper functioning of the project cycle management system.
  • A review of the various committees, which oversee project planning, and approval, and financial approval process reveals that some committees operate at a level which is too high and which should be primarily controlled by the technocrats. In such cases, the decisions of the technocrats should be primarily reviewed by these higher bodies and ratified where warranted.
  • Staffing constraints and inadequate skills is a common complaint and is a contributing factor in the improper functioning of the process. Ministries lack planners and properly trained staff to identify and monitor projects; the PWD is overburdened; and the DPU cannot accomplish its functions with only three Economists who are not very experienced in operations of a project cycle management system.

 

Specific

  • While it is acceptable for projects to originate and be developed by different sources, it is important for the planners to be involved in the process In this case, the DPU although being mandated to develop and appraise projects, is being by-passed by the ministries/agencies who submit an idea as a project to the ministry of Finance for inclusion in the budget. The Ministry of Finance should re-direct these new projects/ideas to DPU for consideration. However, they contribute to the breakdown in the process by allowing the projects to enter the budget. if this practice continues, the Ministry of Finance will not have the moral authority to reject projects from executing ministries which breach, the regulations. This practice has also contributed to the technocrats (Permanent Secretaries, senior officials) not having an indication as to the point in which a project enters the cycle.
  • As a result of the above, projects enter the budget at any time in the year, often through supplementary estimates. This does not promote effective nor efficient planning from both an economic, social and fiscal point and should be discouraged at all levels.
  • There is not a formal selection criterion for projects to enter the PSIP and eventually the budget. Selection criteria developed by the DPU and based on government priorities should be passed to the ministries to enable an in-house first round of prioritisation of project ideas by the Permanent Secretary before they are submitted to DPU.
  • Because the projects do not go through the proper channels, there is an inadequate phasing of projects in the PSIP, over-utilisation of physical resources, the incapacity of ministries and PWD to implement projects and the resulting under-utilisation of financial resources.
  • There is inadequate project planning due in part to staff constraints and the lack of appropriate skills within the ministries and DPU. Projects run the risk of not being consistent with macro/national and sectoral plans and being poorly designed. Poorly designed projects lead to delays in project implementation, stated objectives not being met, frequent reformulation and re-scoping of projects, as well as time and cost overrun. Time and cost over-run is evident among some projects currently under implementation.
  • A common complaint was the lack of good project management skills within the ministries and PWD. Some managers are not properly trained to manage large and complex projects. It was noted that it was the same-engineers who have to manage and monitor the projects resulting in incomplete project information, and improper monitoring of the projects. The executing ministries should in fact be playing a more active role in the monitoring of their respective projects, while allowing DPU and MOF to do monitoring of all projects at the macro level. It was also reported that due to staff constraints at PWD, implementation for some projects have been badly delayed as plans and drawings were not done despite the passage of the initial start-up date.
  • It was found that the lack of information on projects at all stages of the project life cycle has contributed to poorly planned and designed projects, unrealistic cash requirements (for both capital and operating costs) and implementation plans, late intervention when projects are going off-track and poor utilisation of resources.
  • An information system to capture and maintain relevant data on projects as they go through the various phases of their life cycle is missing. It is extremely difficult to keep track of all projects manually. The lack of a formal system can lead to wrong information on projects being used in the decision making process and a replication of data, often not in the same time-frame. In this regard, Ministry of Finance has access to the existing Accounting Information System, while DPU does not and as such is lagging behind in knowledge of expenditure on projects. This means that the DPU cannot readily advise government on the allocation projects should receive for new financial/budget year on an ongoing basis.
  • There is no standard format for reporting-project ideas and as such one should be developed. . As previously suggested, the logical framework used by the EDF is an effective. tool and should be utilised. The use of Project Dossiers to report on all projects should be encouraged and be enforced. It is not satisfactory for the DPU to be the only body utilising this report. A library of these documents should be maintained for reference purposes.
  • Monitoring targets and mechanism have not been identified in the system. The Ministry of Finance does not insist on a detailed cash flow and implementation plan as a pre-requisite for receiving funding. If monitoring targets are done for each project, then it will be easy to identify work-actually done on a project and the associated cost.
  • Project managers are reporting percentage completion when it would be more accurate to report on the status of the various components on the projects and the expenditure on each component to date. This would greatly assist in alerting the authorities when projects are likely to experience cost and time overruns. This is necessary now as the country is embarking on large, complex and expensive projects.
  • PPRAC appears to be focusing on monitoring of projects instead of the planning process and the composition of the PSIP. PPRAC needs to be refocused and allow the Capital Projects Monitoring Committee to carry out its function of monitoring capital projects.
  • There is reported under-utilization of funds on many projects. There are instances where more than 70% of funds allocated for the budget year is not used by the project and so has to be revoted the following year on the provision of adequate justification. This should not be allowed to continue as this practice results in the "tying up" of resources which could be better utilised elsewhere.
  • The DPU has suspended preparation of the PSIP. They should resume the preparation of the PSIP, as it is a valuable tool in planning and sourcing financing for projects. It is understood that local financial institution are interested in seeing the PSIP so that they can identify the areas they would like to fund.
  • There is not an integration between the PSIP and budget to ensure there is not a large gap between financing requirements envisaged in the previous year and that is recommended as the budget for the up-coming year.
    Issues in PSI  (html)
    80b
    Issues in PSI (Word)
    22k
    Issues in PSI  (pdf)
    84b

 


Contact Us | Disclaimer | Administration
BVI Government Gateway Link | Downloads and Archives | Website Directory

Webmaster: Jerinice Stoutt
Website designed and created by CPMD
This page was last updated on: Monday, 21st November 2005

people have visited this site.