Feasibility Studies
and Consultancies
Undertaking a project of this
magnitude requires a number of planning ,economic, financial and environmental studies at
the opportunity, pre-feasibility and feasibility levels before physical progress becomes
apparent. It therefore is likely that a number of different consultants would have to be
engaged and their activities would have to be co-ordinated.
Feasibility studies of various
levels began as far back as 1985 in the Development Planning Unit and are still continuing
today (the airport management).
The first opportunity study was
executed by the Development Planning Unit in 1985. This study was sought to determine if
there was an economic case for a new airport terminal building. It also identified sources
of financing and took about 6 months to complete. This study was quickly followed up with
a study by the Organization of Eastern Caribbean States (OECS) Economic Affairs
Secretariat (EAS) given that the European Development Fund (EDF) regional pool of
resources had been identified as a financing source. This study was compliments of the
OECS.
Once two OECS countries agreed to
the allocation of about 5.0 mecu for the project, Plesseys Airports undertook a study at
their own expense to provide for a new terminal building and a small extension to the
runway. As the Plesseys Airport study was not a detailed one and ideas about a jet airport
begun to be concretized, the United kingdom government sponsored a small study by Sir.
Alexander Gibb & Partners. By now a firm decision had been made to extend the runway
to accommodate jet.
Upon successful application for the
EDF grant the Greek consultant DESIGN, SA was engaged to undertake architectural-
engineering designs of the airport terminal building with related parking for aircrafts
and cars. Within about two years this design was completed and a loan of $5.0 mecu was
officially sought from the European Investment Bank. The technical advisers to the EIB
rejected the design on the basis that there was no master plan for the airport.
The EIB then, at their own expense
and in consultation with the Government of the BVI, engaged the services of the Dutch firm
Netherlands Airports Consultants (NACO) to prepare a master plan Beef Island airport for
the next 20 years. The completed master plan identified the optimal length of the runway,
the various phases of development and parcels of land required for the future. From this
master plan government decided that the runway would not exceed 5,000ft and agreed
on two major phases of development; namely 1A which is the terminal building, landside
infrastructure and airside infrastructure and phase 1B, the extension of the runway to
5,000ft to accommodate small jet as well as to provide for safer operations.
The Dutch consultants were further
engaged in a major way to undertake full architectural-engineering designs of the airside,
landside and terminal building. Including public consultations, this exercise took about
two years with approval by the financial agencies EDF and EIB. The study produces a
building more than four times the existing building with a parking space of 250,000 meters
for aircrafts and space to park more than 300 vehicles in total. In addition, this master
plan identifies the areas for all utilities, fuel, cargo handling facilities and other
aviation related facilities including a relocated and upgrading control tower together
with civil aviation admission
For yet another consultancy, NACO
was engaged to execute the feasibility study for the extension of the runway. These
consultants were chosen to ensure consistency of design quality and continuity of
liability across the design of all airport functions. In fact NACO has worked on more than
200 airports world-wide including some of the largest and busiest in the world. The phase
1B detailed designs have been recently completed and tenders are expected soon. The
Caribbean Development Bank (CDB) has already approved a loan of approximately $15.0
million making it the major funding source.
The Environment Impact Statement
(EIS) and the Environment Impact Assessment (EIA) have been completed by VI Marine
Advisors Inc. and Scott-Wilson of the United Kingdom, respectively. Both the EIS and EIA
were financed by the UK Government. As well both studies were used by the NACO consultants
in the design of the marine works.
The final consultancy on management
of the new facility is out to tender and it is expected to advise on the appropriate
structure for management of assets worth more than $100 million ultimately.
|